Planning & Scheduling Engineer

Planning & Scheduling Engineer, Dubai Petroleum Company, Offshore oil & gas producing installations

START Date: 
November, 1999
END Date: 
March, 2001
  • Responsible for Planning & Scheduling of Planned Preventative Maintenance, Corrective Maintenance, Shutdown and Project activities and Rig schedules for 430 personnel on two offshore oil & gas producing installations and 40 satellite platforms in the Persian Gulf.
  • Supervisor to two Schedulers, six contract planners, two SAP data entry clerks and two logistical operators.
  • Member of the Maintenance Development Team.
  • Tasked with implementing DPC’s integrated long-term Offshore planning hierarchy, procedures and the installation of professional project manag

Planning & Scheduling Engineer, SEW Infrastructure Ltd. , Power Plants & Steel Plants

START Date: 
July, 2008

¤  Planning, Scheduling, Monitoring & updating on Primavera P6/MSP by making L2 and L3 Schedules for all phases covering in Engineering, Procurement & Construction (EPC).

¤  Management Information System(MIS) prepared (Frequency - Monthly):

·       Statement of Planning (applicable Baseline) vs. Achievement &"S - Curve".

Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
4000

Planning & Scheduling Engineer, SKM, Nuevo Nivel Mina - El Teniente - Codelco - Enginering & Procurement (EP)

START Date: 
January, 2011
Sinclair Knight Merz (Chile Jan-2011 to date Planning and Scheduling Engineer Project: EP Nuevo Nivel Mina – El Teniente (jan-2011 to date) VP Codelco 1. Progress Control: Enginering & Procurement Master Plan 2. Procurement Status Report 3. Global Procurement Progress

Planning & Scheduling Engineer, SKM, Nuevo Nivel Mina - El Teniente - Codelco - Enginering & Procurement (EP)

START Date: 
January, 2011

Sinclair Knight Merz (Chile)

Jan-2011 to date

Planning & Scheduling Engineer

  • Project: EP Nuevo Nivel Mina – El Teniente (jan-2011 to date) VP Codelco
    • Progress Control: Enginering & Procurement Master Plan
    • Procurement Status Report
    • Global Procurement Progress
    • Project Road Map

Planning & Scheduling Engineer, Thai Woo Ree Engineering Co. Ltd., PTT

START Date: 
June, 2011

Develops Level 1,2,3 Project Schedule and Critical Path Analysis for assigned project to be submitted to client for approval. Update schedule in weekly and monthly basis, and monitors site progress.

Planning & Scheduling Engineer, Technip, EDF EPR Project

START Date: 
November, 2010

Planning & Scheduling assitance to EDF Project Control Team for Hinkley (United Kingdom) and Penly (France) EPR Projects.

Planning & Scheduling Engineer, SICIM, SpA, M'Boundi Gas Gathering Project

START Date: 
January, 1977
END Date: 
April, 2012

PLANNING ENGINEER – For the on-going Pipeline Network (Trunklines, flowlines) Construction and oil plant revamping. Project location: M’ Boundi Industrial Estate, M’ Boundi, Republic of Congo ( Client: ENI Congo )

 

a.        Assigned to assist Project Manager, Superintendents and supervisors in monitoring construction activities. Ensure that the approved Project schedule ( in Primavera P3 )  is tracked as to actual progress.

Planning & Scheduling Engineer, Siemens AG, •Al Shuweihat S1 Combined Cycle Power Plant (Capacity 1500MW Power & 100MIGD Water)

START Date: 
April, 2002
END Date: 
June, 2004
  •  Prepare and maintain Project schedule;
  • Assign milestones for Contractors for close monitoring of activities;
  • Prepare Weekly (six weeks look ahead) and Monthly reports for Client;
  • Evaluate variance of schedule with actual against planned and advice the concerned Contractor for sequence change or accelerations;
  • Verify the scope of each Contractor against Contract in co-ordination with Contract Adminstrato