PROJECT CONTROLS MANAGER | GALLIFORD TRY 

    ·     Responsible for improving P

Experience Hours (Planning & Scheduling): 
1750
Experience Hours (Cost Management): 
1750
Experience Hours (Forensic Analysis): 
700

Change & Project Controls Manager, Galliford TRY, Southern Water Waste and Water Framework AMP6

START Date: 
December, 2018

PROJECT CONTROLS MANAGER | GALLIFORD TRY 

    ·     Responsible for improving P

Experience Hours (Planning & Scheduling): 
1750
Experience Hours (Cost Management): 
1750
Experience Hours (Forensic Analysis): 
700

Change & Project Controls Manager, Galliford TRY, Southern Water Waste and Water Framework AMP6

START Date: 
December, 2018
END Date: 
September, 2020

PROJECT CONTROLS MANAGER | GALLIFORD TRY 

    ·     Responsible for i

Experience Hours (Planning & Scheduling): 
1750
Experience Hours (Cost Management): 
1750
Experience Hours (Forensic Analysis): 
700

Change & Project Controls Manager, Exelon Nuclear Generation/Bechtel/Shaw, Nuclear

START Date: 
October, 1991

Specialized experience that includes experience that demonstrates knowledge of the principles, practices, and processes of Project Management/Project Controls. Along with my many other duties within the Nuclear Project Management department, I served as the departments innovation lead and have both my PMP Project Management Professional and AACE certifications. My background is diverse, and I excel at data gathering and analytics.

Experience Hours (Planning & Scheduling): 
30000
Experience Hours (Cost Management): 
40000
Experience Hours (Forensic Analysis): 
33850

Change & Project Controls Manager, CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION (CPECC), Alger Refinery Rehabilitation and Adaptation Algeria

START Date: 
January, 2017

ProjectControlResponsibilities

-      PreparedandgetapprovalfromClientforProjectcontrolproceduresincorporatingClient(ADCO and Sonatrach)project & co-operatestandards.

-      DevelopedandgetapprovalofWBS,CBSandOBS

-      DevelopandgetApprovalofPlanningPackageforEPCCandWBSforlevelIIIandIVschedule

Experience Hours (Planning & Scheduling): 
1800
Experience Hours (Cost Management): 
900
Experience Hours (Forensic Analysis): 
300

Change & Project Controls Manager, CHINA PETROLEUM ENGINEERING & CONSTRUCTION CORPORATION (CPECC), Abu Dhabi, Mender Field Development Project Phase I

START Date: 
May, 2014
END Date: 
December, 2016

ProjectControlResponsibilities

-      PreparedandgetapprovalfromClientforProjectcontrolproceduresincorporatingClient(ADCO and Sonatrach)project & co-operatestandards.

-      DevelopedandgetapprovalofWBS,CBSandOBS

-      DevelopandgetApprovalofPlanningPackageforEPCCandWBSforlevelIIIandIVschedule

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
500

Change & Project Controls Manager, Arrow Energy (Shell/PetroChina JV), Bowen & Surat LNG Project, Pipelines and Upstream Development

START Date: 
November, 2011
END Date: 
November, 2015

•Responsible for a portfolio of facility construction and pipeline projects range from $10 million to $13 billion during all phases of project development and execution.

•Developed and implemented comprehensive monthly reporting package encompassing all project activity, progress measurement, change management, risk management and in-depth analysis of variations from baseline plan & budget.

•Implemented integrated schedule management to cover all aspects and phases of planning & scheduling.

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
8650
Experience Hours (Forensic Analysis): 
1750

Change & Project Controls Manager, Turner Industries Group, Impala Terminals Burnside Coal Storage Facility

START Date: 
February, 2014
END Date: 
November, 2014

I was brought to the construction management team, near the end of the project, to implement the missing project controls structure required of a $300 million project.

Experience Hours (Cost Management): 
1150
Experience Hours (Forensic Analysis): 
700

Change & Project Controls Manager, Bay, Oil Platfrom fabrication & installation

START Date: 
January, 1986
END Date: 
January, 1990

►     Bay Ltd./Berry Industries, Corpus Christi, TX,  1986 to 1990 (LS Projects)

Change & Project Controls Manager, AECOM, TNRP, Flood Recovery, Easing Sydney Congestion

START Date: 
July, 2006
END Date: 
April, 2016

Project Controls Manager

Lead a tram of project controls staff on programs and projects in civil infrastructure.

Experience Hours (Planning & Scheduling): 
5500
Experience Hours (Cost Management): 
15400
Experience Hours (Forensic Analysis): 
1000