Michelin Tyre Factory, Phase 02 – EPC, Chennai:
Project Scheduler, Responsible for the Planning and scheduling of the EPC Project (75,000 Sqm). Performed key functions like Master Construction Schedule, L4 Schedule, Resource Planning, Site Planning, Procurement Matrix, Design Schedule, Client Interface Schedule, Vendor finalization support, Project Budget formulation, S Curves (Financial & Progress) Vendor Bill Certification Report.