planning and cost control engineer, BUTEC, BUTEC - CP69 Perimeter Security Systems Enhacement at NDIA
START Date:
March, 2011
END Date:
January, 2012 Supervise Daily, Weekly and Monthly reports production and submission to the client.Update and maintain the Contract Master Schedule and four weeks look ahead report.Issue and maintain the production rates report.Issue and update the material tracking system and the project schedule of submittals.Prepare and submit the Interim Monthly Statement.Prepare the project Budget, cash flow, resource , matrial and equipment histograms.Evaluate subcontractor schedules and align it with the contract master schedule.
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: