SENIOR PLANNER,PMO,CLIENT SIDE (Qatar Rail), DB International, DOHA METRO RAIL PROJECT
START Date:
August, 2016 Currently working as Senior project Planner for Doha Metro rail project under PMO ,Qatar Rail.
I am respeonsible for Contractor/PMC schedule analysis and approval ,Project control & interface planning.
- Prepare & update the integrated Master schedule for Metro Phase-1 in P6.
- Critical path analysis for Overall Metro -1 & work Packages in P6.
- Review & Analysis of detailed schedule submitted by package Contractor.
- Review & Analysis of Lev-2 schedule submitted by package PMC.
- Updated the Integrated(Civil & Systems) schedule for Metro-1 in TILOS chart.
- Responsible for analysis,review & impact assesment for Overall Systems & Major stage work scope.Coordination/Meeting with respective PMC & contractor as & when required.
- Review & comment for enhancement of the cocntractor/PMC schedule with respect to logic,sequence,technicality & content.
- Tracking & Monitoring of Interface dates (Civil & Systems) ,issues , impact assesment & coordination with related packages.
- Prepare & tracking of SRP (Safety review pannel) schedule for Overall Metro Phase-1. Coordination with QR Service delivery & systems assurance team .
- Schedule quality check & comment through SRS (Scherdule review sheet)
- Weekly PMCS report review & quality check with comment/suggestion.
- Monthly PMCS report review & qaulity check with comment/suggestion.
- Support QR –PMO Director through presentation slides,tracking & monitoring sheet ,analytical reports as and when required.
- Support PMO reporting team for development of PMO monthly progress report.
- Company: