Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Project Planner, ETA - ASCON, Dubai, UAE, 3B+GF+12F+LR+UR+Swimming Pool Hotel & Apartment Bldg at Al Raffa, Dubai owned by Al Ghurair Investment LLC

START Date: 
October, 2008
END Date: 
May, 2009

Planning Engineer/ Project Planner, assisted Project Manager in the monitoring and updating of site progress, resource utilization, and cash flow of Al Raffa Proj. Prepared monthly and weekly progress reports on site. Monitored and updated all the subcontractor’s construction programme, resource histogram, shop drawing submission and material procurement schedule. Coordinate between client, consultant and subcontractors on all site and progress related issues. Prepared monthly cost presentation for the company’s internal monitoring of cash flow. Assisted in stakeholders communication, identifying what is to be done, when, and by whom. Also prepared extension of time claims for substantiation and approval of the Consultant and Client.