Fluor

Kit Mendoza

First Name: 
Kit
Last Name: 
Mendoza
  • Planning and Scheduling, Cost Management, Change Management, Earned Value Management, Risk Management, Proposals, Project Initiation, Execution, Monitoring and Controlling, Project Close Out, Documentation, Staff Recruitment and Retention, Maintenance and Operation, Boiler, Water Treatment and Wastewater Treatment

Professional Since: 
Nov-2000 (24.0 yrs experience)
Years Experience: 
0

Lead Cost Engineer / Lead Scheduler, Fluor, OTIA III Bridge Program, Eagle Commuter Rail Project, US 183 South Project

START Date: 
June, 2007
END Date: 
October, 2016

US 183 South Project - Austin, TX

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
500

Tom Perlman

First Name: 
Tom
Last Name: 
Perlman

Director, Project Controls for major engineering, procurement and construction projects as well as providing functional oversight at the corporate level. Experienced in domestic and international construction and industrial methods, materials and execution. Effective in developing, implementing and managing programs and reaching project goals. Excellent communications skills. Demonstrated ability to successfully interface with all Project and Client entities.

Professional Since: 
Jan-1997 (27.8 yrs experience)
Oldest experience: 
Jan 2015 (9.8 yrs experience, WARNING: 18.0 years variance with Professional Since)
Years Experience: 
2
Guild Accreditation: 
GPC Member
GPC Member Since: 
Wed, 2016-05-18 (All day) - Wed, 2055-05-05 (All day)

Senior Director Project Controls, Fluor, Citrus County Combined Cycle Project

START Date: 
March, 2017

Responsible for all Project Controls functions including planning and scheduling, cost and change management, progress management and risk management

Alphons Bruns

First Name: 
Alphons
Last Name: 
Bruns

Specialist in:

  • Building planning code, WBS structures and project control in Primavera Software.
  • Planning Management and running a planning department.
  • Forensic Planning, Change- and Risk Management, Advice in Complex Environments, Software Implementations, and Systems Engineering.
  • 4D planning and Time Line Diagrams

I worked 20 Years in the role of process technician and commissioning engineer in the process industry, oil&gas, chemical and product finishing.

Professional Since: 
May-2001 (23.5 yrs experience)
Oldest experience: 
May 2001 (23.5 yrs experience)
Years Experience: 
15
Guild Accreditation: 
GPC Member
GPC Member Since: 
Mon, 2017-03-27 (All day) - Wed, 2055-05-05 (All day)

Basebuild Scheduler, Fluor, Base Build of Intel’s Aloha site

START Date: 
September, 2012
END Date: 
September, 2013

Basebuild Scheduler for Intel for gown room conversion & data center upgrade.

Experience Hours (Planning & Scheduling): 
2000

Construction Planner, Fluor, $1.3 billion OTIA III bridge repair/replacement program

START Date: 
September, 2004
END Date: 
September, 2012

Responsible in the planning & schedule managment efforts for Oregon Department of Transportation's 1.3 billion OTIA III program that replaces or repairs 365 of the State's critical bridges with the objective of increasing capacity on main transportation routs.  Responsibilities include construction analysis & claims resolution, schedule maintenance, progress updates, cash flow changes, tracking deliverables, A&E contract schedule review, CEI budget development & monitoring, change management, and providing various reports used in the monthly reporting process.  Als

Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
8000
Experience Hours (Forensic Analysis): 
500

Sr. Project Controls Specialist – Planning & Scheduling, Fluor, Cerro Verde process plant expansion (Freeport McMoRan)

START Date: 
March, 2015
END Date: 
July, 2015

Area 2 planning (Grinding, Wet Area, Tailings Thickening and Moly plant) on the process plant expansion project (from 120 Kt/d to 360 Kt/d) of Cerro Verde copper production unit (client: Freeport McMoRan).

Experience Hours (Planning & Scheduling): 
500

Senior Planner, Fluor, SABIC Elastomers Project

START Date: 
January, 2007
END Date: 
January, 2011

Lead Planning Engineer within an Integrated Client/PCS Project Management Team (P.M.C), responsible for the fully integrated planning for a US$ 4bn Elastomers project for SABIC and Exxon Mobil within Saudi Arabia, over two sites.

Roles included development of L2,3,4 project schedules,interface management, development of project control procedures.

Experience Hours (Planning & Scheduling): 
6500
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
1000