Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Senior Planner

Senior Planner, Black & Veatch Corporation, Multiple

START Date: 
May, 2002
END Date: 
October, 2005

Responsible for all aspects of project planning for BVL (Black & Veatch Limited) within the DCWW (Dwr Cymru Welsh Water) South East Alliance. Duties included the production, development and monitoring

of programme and project schedules for all types of projects controlled by BVL. Development of project control reports, including EVM, for the current & future AMP periods.

Experience Hours (Planning & Scheduling): 
6800
Experience Hours (Cost Management): 
1600

Senior Planner, Hitachi Rail Europe, Intercity Express Programme (IEP)

START Date: 
May, 2016
END Date: 
March, 2019

Lead Planner (Intercity Express Programme)

 

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
250

Senior Planner, Balfour Beatty Construction Services UK; Balfour Beatty Regional Civil Engineering, SHETL Framework; Inveramsey Bridge; Moray Framework

START Date: 
November, 2014

Senior Planner, Balfour Beatty CSUK Regional Civil Engineering, North Scotland.

SHETL Framework Substations, Inveramsey Bridge, Moray Frameworks.

Senior Planner, Interserve Construction Limited, Hospitals inc. P21 / P21+, Schools inc. BSF, Colleges, Universities, Offices, Retail

START Date: 
March, 2005
END Date: 
March, 2013

My experience covers both tender and construction stage planning. I have also fulfilled a dual role of acting as a Design Coordinator.

Planning Manager, Senior Planner, London Underground, Parsons Brinkerhoff, London Underground Station

START Date: 
October, 2003
END Date: 
August, 2007
Planning Manager, Senior planner providing planning support to the London Underground Station Modernisation and Upgrade programme. Line Upgrades. Master Projects Database MPD setup and delivery. Earned Value.

Senior Planner, Balfour Beatty Regional (Mansell Construction / Dean & Dyball), Various

START Date: 
March, 2008

Current Role

I started as lead Planner with Dean and Dyball Civil Engineering / Construction, which partly became Mansell Construction following the Balfour Beatty acquisition of 2008.

Originally, I was Ringwood’s lead planner tendering single- and two stage projects generally in the £1m-£20m range, both negotiated and frameworks.

Tenders and projects generally either used the JCT or NEC3 forms of contract, with occasional use of GC Works 1.

Also in Ringwood, I was a member of the Regional Safety Committee, and was elected a staff representativ

Senior Planner, BAM Construction, (various projects)

START Date: 
April, 2002

Senior Planner currently living and working in the Somerset area.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content