Hatch Associates Pty Ltd

Project Control Engineer, Hatch Associates Pty Ltd, Koniambo Nickel Mining Project

START Date: 
June, 2012
END Date: 
May, 2013

Projects Executed

Ø    Koniambo Nickel Project – Construction of Nickel Refining Plant at Koniambo Massifs in New Caledonia (a 60,000-tonne-per-annum ore processing facility developed by a joint-venture partnership between Xstrata Nickel and SMSP New Caledonia. Hatch - Technip joint-venture is designing and constructing the project with Chinese & Korean companies (CMIIC, Doosan etc) as construction contractors.)

 

Major Responsibilities

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000

Ameenulla Soofi

First Name: 
Ameenulla
Last Name: 
Soofi

I"m an well experienced Project Planner with working experience in Planning and Scheduling principles by effectively using Primavera P6 and MS project for schedule development, resource / cost loading, schedule / CPM analysis and Project Reporting.

Professional Since: 
May-2011 (13.7 yrs experience)
Oldest experience: 
Aug 1997 (27.4 yrs experience, WARNING: 13.7 years variance with Professional Since)
Years Experience: 
11

Project Planner, Hatch Associates Pty Ltd, Various Coal Mining Projects

START Date: 
May, 2011

As a Project Planner in HATCH, Australia – one of the leading EPCM multinational organisation, working for Grosvenor, Moranbah South & Dartbrook PFS, FS & implementation (coal mine development) projects in Bowen Basin of QLD for Anglo American Metallurgical Coal, gathered contract scope, prepared schedule basis, carried out schedule development, integrated various subcontractors schedules into a master schedule, prepared cost & resources loaded schedules, estimate & analyse man-hours distribution, generate & freeze project baselines, report project critical path, pr

Mudassir Khurshid

First Name: 
Mudassir
Last Name: 
Khurshid

MYSELF:
9+ years experienced Mechanical Project engineer; Expertise in project planning (Primavera P6); Dedicated, numerate & very organised
Developed skills in Project Plans, Maintenance Plans & Support staff plans; Embedded culture of continuous improvement & teamwork
Well understood the vital people side issues to get organisation wide buy-in
Excellent: Communication skills; Time management; Effective workability under pressure; Trouble shooting & technical capacity

PROJECT MANAGEMENT: CONCISE PLANNING, A

Professional Since: 
Jun-2011 (13.6 yrs experience)
Oldest experience: 
Jun 2011 (13.6 yrs experience, WARNING: 0.0 years variance with Professional Since)
Years Experience: 
0

Planner / Controls Engineer, Hatch Associates Pty Ltd, GEMCo

START Date: 
June, 2011

 

Planning / Controls Engineer

Hatch

Privately Held; Mining & Metals industry

June 2011 – Present (4 months) NSW, Australia

PROJECT: GROOTE EYELANDT EXPANSION PROJ

Planning / Controls Engineer, Hatch Associates Pty Ltd, GEMCo (Manganese Mine)

START Date: 
June, 2011

Planning / Controls Engineer

Hatch

Privately Held; Mining & Metals industry

June 2011 – Present (4 months) NSW, Australia

PROJECT: GROOTE EYELANDT EXPANSION PROJECT (Manganese Mine / GEMCo) - PH

Construction Planner, Hatch Associates Pty Ltd, Voisey's Bay Nickel Commercial Plant

START Date: 
September, 2008
END Date: 
April, 2009

Project Planner, Voisey's Bay Nickel Commercial Plant, US$3 billion nickel refinery in Newfoundland, Canada

Graham Hanna

First Name: 
Graham
Last Name: 
Hanna
Professional Since: 
May-1995 (29.6 yrs experience)
Oldest experience: 
Jul 2009 (15.4 yrs experience, WARNING: 14.2 years variance with Professional Since)
Years Experience: 
1

Rehannon Sanderson

First Name: 
Rehannon
Last Name: 
Sanderson
Professional Since: 
Aug-2006 (18.3 yrs experience)
Oldest experience: 
Sep 2008 (16.3 yrs experience, WARNING: 2.0 years variance with Professional Since)
Years Experience: 
2

Wayne Thurgate

First Name: 
Wayne
Last Name: 
Thurgate
Professional Since: 
Feb-2008 (16.8 yrs experience)
Oldest experience: 
Sep 2002 (22.2 yrs experience, WARNING: 5.4 years variance with Professional Since)
Years Experience: 
7

Market Place

No results found... (try selecting a different content filter)