Master scheduler for all maintenance interventions requiring unit shutdown / turnaround on the platform. Our maintenance cycle is 6 years during which time we preform 5 major interventions and several dozen smaller ones including;
2 Nafta Cracker complexes
2 FCCU complexes including one HF alkylation plant
CCR complex incl ARDS
Cat changes
Regular unit decoking / cleaning
I run a team of between 3 and 6 schedulers. TA Budget for planning and execution varies between 50 and 150 Million Euros per year (average +/- 75M euros)