as-built progress

SUB AGENT, Edmund Nuttall UK, Tunnels

START Date: 
August, 2006

Sub Agent for a civil engineering contractor looking to get into project and programme management roles.

Duties

Short term (quartely) planning for a section of works in a civil engineering project using MS Projects

Montoring and updating progress

Project Planning Engineer, Anon Construction, New Build Projects

START Date: 
April, 2012
Creating & monitoring programmes using ASTA PowerProject from tender stage to construction stage including short term, finishing, as-built & procurement programmes Ensuring critical path & float are easily identifiable for all stakeholders and relationships, durations and logic is evident Providing site team with daily, weekly and monthly reports along with activity monitoring & progress charts Reviewing & analysing contract documents at tender stage to compile accurate tender programmes incorporating labour resources & materials

Senior Planning Engineer - Civil Work, Simplex Infrastructures Limited, Messaide, Messaide 2000Mega Cycle Power Plant, Qatar

START Date: 
September, 2007
END Date: 
March, 2009

-Provide Baseline Schedule for all infrastructure activity.

-Provide Clear and concise WBS, Contract Milestone, Scope of Work and deliverables.

-Provide Progress graphical and narrative Report

-Update schedule and determine activity that our delay 

-Attend regular meeting 

-Provide MS Excel forecasting report