Chicago Bridge & Iron

Primavera Project Scheduler, Chicago Bridge & Iron, Coal Fired Power Plant

START Date: 
May, 2015
END Date: 
October, 2015

May 2015 – October 2015      Four Corners Power Plant (APS), Fruitland, NM

                                    Primavera Overhaul Scheduler (May 27, 2015 – October 29, 2015)

Hired by Chicago Bridge & Iron to build a P6 Project at Four Corners Power Plant for their Unit 5 Major 2016 Overhaul.

Experience Hours (Planning & Scheduling): 
150