Baseline and Layers

1 reply [Last post]
Alexandre Faulx-B...
User offline. Last seen 2 years 30 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355

Hello PPers,

Is it possible to assign two different layers to the current task and its baseline?

Thank you

Replies

Thorsten Balthasar
User offline. Last seen 10 years 18 weeks ago. Offline
Joined: 14 Jun 2011
Posts: 15
Groups: TILOS

Alexandre,

No, task and baseline has the same layer, but:
if you want to switch off the visibility of selected baseline tasks you may use the "Visible" flag in the baseline manager.

regards

Thorsten