Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Assign other progam as a baseline -Synchro

2 replies [Last post]
abusen suliman
User offline. Last seen 4 years 18 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 12

 Hi there,


 have 2.sp files and both has been  exported form P6. one is baseline(No progress) and other is updated .
how can I assign the baseline over the updated one ?

Thank you

Replies

Renzo Constenla B...
User offline. Last seen 14 weeks 1 day ago. Offline
Joined: 23 Mar 2011
Posts: 21

Dear colleague:

 

proceed as MR. PT Thomas described.

Just take care that each activity in one file match with the right activity in the other file, through the Act ID.

This is the only way for P6 to joint the current activity with its baseline.

Regards 

PT Thomas
User offline. Last seen 5 years 37 weeks ago. Offline
Joined: 18 May 2018
Posts: 9
Groups: None

1. Import Both Files to Primavera 

2. Create baseline for the baseline program  

3. After restore baseline and it will be restored to Program Menu as baseline-1

4. Then Open the program which you want to assign the baseline

5.Go to maintain baseline -> add -> Select convert another project to a new baseline to the current project and select baseline-1 form project menu

6. Go to assign baseline and assign newly added baseline to the project