Im working on a project with a critical sectional completion date of 31/3/14
On the critical path is release of a key area by another project
This other project is approx 18 months work, but its start is being delayed by client due to financial approval
Plugging in the delayed start of this other project gives us approx 12 weeks float on our sectional completion. This represents approx 5% of the total time from now to 31/3/14
I dont have access to the other project programme, and I cant find any details on why the finanical approval of it is being delayed
So thats the situation. I want to povide a confidence level that my project will hit its completion date, but without the details behind financial approval activities and the others projects programme, I dont know how to go about running a Monte Carlo analysis or anything.
Any suggestions or rules of thumb I could apply here? I havent done much schedule risk analysis before, so I dont want to have to trust my gut feel.
Thanks in advance,
Gary
Replies