Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost of Project Controls- is there an industry standard?

1 reply [Last post]
Amir Vaziri
User offline. Last seen 5 years 27 weeks ago. Offline
Joined: 17 Sep 2009
Posts: 10
Groups: None

Hi,

does anyone know if there is any industry standard rate for project controls as part of the overall project value. I know that it can be different due to the nature of the project, scope of project controls, etc and it must be around 3-5% of overall budget but more wanted to see if there is any valid research or standardised approach behind it?

Regards,

Amir

Replies

Ahmet Tuter
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 7 Feb 2013
Posts: 52
Groups: None

I can not answer you as far as the research, but from experience, Yes that % seems reasonable. Now I am going to write from a General Construction Contractor Standpoint. When you make a budget for a project, the project management cost (which includes the people who will do project controls) is included part of the general conditions (or general costs whatever you call it). And this general conditions is usually anywhere from 5-15%. Deduct things like your jobsite trailer, office equipment, fire watch, safety etc... you are left with 5% at the most for the whole project controls + site supervision. Deduct site supervision and you are left with around 2-5% just for project controls. from the jobs I worked on I can tell you that this would be the average.

In order to be a little more scientific, you can use the total number of project management hours needed per a certain scope or dollar value of a job by using your historical data from previous jobs. Another approach would be to take your schedule, multiply the duration by the cost of the PM staff that you know you will need for that size of job (of course dont forget that at the beginning and end of the job you will need less PM staff). One thing I just remembered was a curve presented in the PMP book that showed staffing needs on a project where it peaked in the middle. You may want to check PMI standards to see if you can see something.