Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

EPC & DB Contracts

2 replies [Last post]
Kannan CP
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

What benefits the Owner can gain by awarding EPC or Design & Build Contract to a Contractor.

For eg:

a. The Owner defines the Scope of work, Specification, Lumpsum Budget, Quality, Duration, Basic design etc.

b. The Contractor has to develop the detail design, drawings, Procure the materials, construction works, hand over the work as per the Owner's requirement specified in the Contract agreement. Since it is Lumpsum payment, the risk of price hike come to Contractor's shoulder.

c. Which type Contract the Owner can select- EPC or DB?- In both type, all the responsibilty comes under a Main Contractor ( or joint venture with a leader), who has to perform the design, eng, procurement, construction and commissioning. Then what is the difference between these two types?

Regards

Kannan

Replies

Kannan CP
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Thanks Mike... to clear my doubt

Mike Testro
User offline. Last seen 36 weeks 2 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Kannan

There is no difference - just different names for same procurement route.

Engineer Procure Construct  is American -- Design and Build is British

The benefit for the employer is that the all the risk of the design - construct interface is with the contractor.

Unless that is the employer insists on checking the design - in which case a lot of the time risk comes back to the employer.

Best regards

Mike Testro