Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How Many Project Planners?

2 replies [Last post]
Philip Richards
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 28 Oct 2009
Posts: 9
Groups: None

Does anyone have a guide as to how to scope the requirement of Project Planners accross a portfolio of projects of varying sizes.

I understand that size & complexity of project and the level of service provided will be influensing factors, but is there a rule of thumb maybe in relation to the number of project managers.  1PP to 1 PM  or  1PP tp every 2 PMs maybe?

 

 

Replies

Shah. HB
User offline. Last seen 35 weeks 1 day ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi Philip

 

I believe it depends on project requirement ,2 or more it depends on the nature of project complexity and contact value

 

Regards

Shahul

Mike Testro
User offline. Last seen 21 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Philip

This is an interesting question.

Some projects are lucky to get any planners at all.

To define terms - a Planner knows how to build the project - a Scheduler knows how to work the software - sometimes the Planner can do both. 

The ideal situation is where a planner creates the programme and then monitors the site progress - probably using a team of assistant schedulers.

A large and complex project may need more than 1 scheduler and 1 scheduler may well be needed to spread over several simpler projects.

The difference between what is needed and what is actually allocated is the main point.

Other factors include:

1. Skill speed and accuracy of the Planner / Scheduler

2. Chosen software - the ability to copy paste between spreadsheets means that data entry can be done in seconds or takes hours of manual input.

3. Company systems and procedures - if a lot of data reports are required - EVA S Curves etc - it will take longer to do than a simple progress update.

4. Form of contract - working on a NEC project will require a lot more planning / scheduling input than - say - a JCT. 

So if anyone has a rule of thumb that will encompass these factors I would like to see it.

What happens in practice is that the minimum number of staff are deployed - up from zero - and only if they are really struggling will extra suport be deployed.

Best regards

Mike Testro