Dear Friends
I am Working on a Palace Project , our project end date was 31 mar 2011 , we submit several impacted schedule whenever we recieve changes and new design , as per our impacted schedule the end date was in novemeber 2011 for the only the released scope , howver there are four to five small building that are part of provisional sums and they have not been released.
The Client grant us extension of time upto june 2011 for released scope only , however this extension is not enough as there are stiill many areas where design is pending and also the completion of work requires an other subcontractor from the client which has not yet mobilized on the site
i have to prepare extension of time documents for my Claim , if any of you have any good format , please email me at Use private message service
Thanks
Umer Mehmood
Planning Engineer
Replies