EQUIPMENT SPECIFICATION FOR 48 INCH PIPELINE CONSTRN

1 reply [Last post]
SANJEEV KOUL
User offline. Last seen 16 years 49 weeks ago. Offline
Joined: 1 Mar 2007
Posts: 18
WE HAVE TO EXECUTE A 48 INCH DIA CROSS COUNTRY ONSHORE PIPELINE 625 KM LONG APPROX.ACCORDINGLY WE HAVE TO SELECT/FINALISE THE SPECIFICATION OF THE FOLLOWING PIPELINE CONSTRUCTION & INSTALLATION EQUIPMENT :-

1) DOZERS FOR ROW CLEARING

2) GRADERS FOR ROW CLEARING

3) HYDRAULIC EXCAVATORS FOR TRENCHING

4) HYDRAULIC EXCAVATORS AS ROCK BREAKERS

5) EXCAVATORS AT THE LOCATION OF PADDING MATERIAL
EXCAVATION AND LOADING FOR TRANSPORTATION.

6) TIPPERS / TRACTOR TROLLEYS FOR SHIFTING PADDING MATERIAL

7) DOZERS FOR BACKFILLING

8) BACHOE FOR SPREADING THE TOP / BOTTOM PADDING MATERIAL
INTO THE TRENCH

9) SIDE BOOMS FOR BENDING (IE BENDING MACHINE )

10)SIDE BOOMS FOR WELDING (MAINLINE WELDING)

11)SIDE BOOMS IF ANY FOR TIE IN LOCATIONS

12)SIDE BOOMS FOR LOWERING

13)CRANE FOR STRINGING

14)BORING MACHINE FOR X-INGS

15)COMPRESSORS , PUMPS ETC FOR HYDROTESTING AND FINAL COMMISSIONING.

THE PIPELINE HAS A NORMAL TOP COVER OF 1M AND A NORMAL TRENCH SECTION WITH 45 DEGREE SIDE SLOPES.SIDE CLEARANCE FROM PIPE SIDEWALL IS AS PER NORMAL PRACTICE.TRENCH DIMENSIONS ARE

i) Bottom width of trench = 2.3 m
ii)Depth = 2.5 m (from NGL)
iii)Top width = 7.45 m
iv)Side slopes = 45 degrees inclination
v)Volume of trench per m length = 12.57 cubic metres.
vi)CSA of trench = 12.57 sqm

AVERAGE LENGTH OF SPREAD HAS BEEN ASUMED AS 70 KM.PLEASE SUGGEST AND PROVIDE ALL POSSIBLE INPUTS ; BASED ON PREVIOUS EXPERIENCE IN 48 INCH PIPELINE EXECUTION ; REGARDING THE SPECIFICATION AND NUMBER OF EQUIPMENT PER SPREAD OF 70 KM AVERAGE LENGTH.

ANY LOGICAL DEDUCTION ETC , FOR EXAMPLE , ABOUT THE LOAD CAPACITY OF SIDEBOOMS , COMPRESSOR CAPACITY FOR HYDROTESTING OR THE SELECTION OF RATING OF EARTHWORK EQUIPMENT ETC ; SHALL BE HIGHLY APPRECIATED AS A SUPPORTING DOCUMENT.ALL THESE DATAILS ARE REQUIRED BY US FOR FINALISING THE PURCHASE ORDERS FOR THESE EQUIPMENT ETC AND ANY ASSISTANCE IN THIS CONNECTION SHALL BE HIGHLY APPRECIATED.
******************************************

Replies

Ben Robertson
User offline. Last seen 16 years 48 weeks ago. Offline
Joined: 24 Sep 2007
Posts: 4
Dear Mr. Sanjeev,

Please see my post to you regarding the 690 kilometer 56" pipeline project you were planning earlier this year.

If you would contact me directly at ben.robertson@sbcglobal.net or through the member to member contact method in Planning Planet, I may can help you.

I work with an European pipeline contractor (to find them work or companies desiring rental of their pipeline equipment and/or pipeline workers) that is interesting in large pipeline construction projects.This company is experienced in the laying of over 20,000 kilometers of all sizes of pipelines up to and including 56" and 60" pipeline jobs.

They are interested in subcontracting such jobs or renting multiple spreads of pipeline construction equipment with or without experienced key personnel, such as spreadmen, foremen, equipment operators, pipefitters, welders, etc. They will undertake work anywhere, including Iraq and Columbia.They will rent out there skilled workers alone, without renting the equipment.I know that they have at least two rental 48" pipe benders, available immediately with or without the experienced operators.

While they normally do not want to sell their equipment, there are available for sale (fourteen) 14 (surplus to needs)brand new - no hours-2007 Komatsu D-355 Pipelayers (the largest made) for sale at present.These are with transferrable factory warrantees. You will need this number and more of this size pipelayers.

If you check on the build-time required at the Komatsu factory and the Caterpillar factory (build time on Cat 587 pipelayers)you will see both quote 8 months to one year.If you have hunted new or used Pipelayers about the world, they are nearly impossible to find at any price.

Upon further information from you, I could get my friend at this company to run the numbers on what and how many pieces of equipment your job would require, and any other advice he may offer.

This company is part of a large consortium, so there is ample equipment, manpower and financial strength within associated members.

Regards,

Ben Robertson