ALL,
We are required by our client to compare actual percent complete vs planned percent complete on our weekly meeting. To report on actual percent complete, I'm using duration percent complete to show actual. I have one issue here, There are two duration percent complete (Duration % complete and Duration % complete original). What is the difference between these two? Which percent complete would show the actual completion percentage? --- thanks in advance.
I thought that BL percent complete would show me the planned percent complete but when i plug in column BL percent complete from the column list, it does not show any numbers/percentages.
I am on the right track in using the BL percent complete to show the planned percent complete? If not, how could determine the planned percent complete as of data date.
THANKS THANKS!
Russell
Replies