Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Original duration (10 days) – Actual duration (5 days) = Remaining duration (10 days)?

7 replies [Last post]
Sergey Shevchenko
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 2 Apr 2013
Posts: 5
Groups: None

Gents, 

Trying to update activities automatically but original duration every time prolongs itself with out changing remaing duration?

Thank you

Replies

Sergey Shevchenko
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 2 Apr 2013
Posts: 5
Groups: None

Thank you!

Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline

Sergey,

All hitting schedule does is to move the data date -it does not automatically adjust remianing duration for you

 

To do this, you need to use the "update progres" function instead (Tools > Update progress)

 

NB: Best practise is to manually adjust remaining duration rather than to use this function, as it is dangerous to assume all started activities have progressed precisely to plan.

 

Cheers,

 

G

Sergey Shevchenko
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 2 Apr 2013
Posts: 5
Groups: None

Gary, 

1) Set ACTUAL START, push F9, click SHEDULE;

2) Yes for ALL. 

Thanks

Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline

Sergey,

 

1) Please explain the procedure you are using to update activities automatically

2) Is this issue occuring for all activities, or just some of them?

Sergey Shevchenko
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 2 Apr 2013
Posts: 5
Groups: None

Thank you for answers!

I'm trying to describe my issue in the picture

1571
dokument1.jpg

Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline

Sergey,

 

1) Please explain the procedure you are using to update activities automatically

2) Is this issue occuring for all activities, or just some of them?

Sendhil Kumar
User offline. Last seen 9 years 26 weeks ago. Offline
Joined: 7 Aug 2010
Posts: 6
Groups: None

Original Duration Never changes. It is the planned time to complete a task.

Actual duration is the time actually spent for a task. (It is calculated as a difference of Actual start date & data date for in progress activities.)

Remaining duration is no of days u require to complete the activity from data date. This to be given by you at the time of updating.

At complete duration is the no of days that would actually be spent to "Complete" a task. This might keep on changing for every update till an activity is completed.