Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Total Float Problem in P6

2 replies [Last post]
Hossam Al-Wazzan
User offline. Last seen 8 years 35 weeks ago. Offline
Joined: 20 Oct 2008
Posts: 3
Groups: None

Greetings,

I have developed a project schedule using P6 v7, with a total float -15 days, when I do 2 weeks lookahead filter, I can see that some activities have positive float and some activities have negative float, the problem is that the total Float for all the project is showing the positive float only! it is neglecting the nagtive float! Why????

 

Kindly advise.

Replies

Zahoor Ahmed Sidd...
User offline. Last seen 9 years 14 weeks ago. Offline
Joined: 30 Nov 2011
Posts: 2
Groups: None

Please advise wheather is it possible generate float curve similar to s curve in p6 or in p3

Abilash Palakkada...
User offline. Last seen 8 years 43 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47

 

Negative float is shown usually when you have finish constrain, the activities which are not in the critical path will have positive float.