Dear Planners,
Greetings!!
I am new to Primavera, i did certification course for the same. I am facing this weird problem in the planning and scheduling that i am doing for a housing project. Following are the details and the related problem i am facing in Primavera p6...
Total Number of Blocks to be constructed: 10 Nos
Total Type of Blocks: Type A,B,C & D.
all blocks are stilt +4 Floors ( only difference being difference in area of each block)
How i scheduled is as follows:
Enterprise - Project SW - Bock A (- Block A1 - Block A2 - Block A3)
- Block B (-Block B1 - Block B2 - Block B3)
- Block C (- BlockC1 - Block C2)
- Block D (- Block D1 - Block D2)
- Land Development.
Total Time to complete the project: 30 Months Starting date 01-03-2013
Maximum time to complete one block ( any type) = 12 months or less.
Since all the blocks are same except the area, what i did i Scheduled Block C1 first. I completed it in every aspect. It showed the activities that were critical and other too as per actual expectation.I had also marked each blocks starting and finishing milestone. Then i copied the same to other blocks ( since all are same), then the problem arose.After i scheduled all the activities turned non critical even the Block C1 turned non critical.
Please enlighten!
Thankyou all
Replies