Curtain from Calendar

Member for

9 years 4 months

Hi Hawken,

 

You can add them manually and colour code them to for each rescource/calendar/subcontractor etc. Maybe this is will give you what you need?

 

Rob

Member for

13 years 1 month

Thank you for the replies.

 

Hawken

Member for

24 years 6 months

Furthermore all non work periods for all views and all projects in a single database are based on the Default Database calendar and changing this calendar will affect all projects and views. This makes P6 P6 particually difficult when you have a number of projects working on different calendars and each project would like to show their own project calendars as non work periods.

 

 

Paul E Harris

Eastwood Harris Pty Ltd

www.eh.com.auwww.eastwoodharris.com and www.primatrain.com.au

Project Control Consultants and Planning and scheduling software book and training manual publishers

Member for

22 years 9 months

Hello,

you cannot link a curtain to a calendar non-working days or months; starting with P6R7, the non-working periods (say: Saturday, Sunday) are shown with a gray zone in the Gantt Chart

Alexandre