How I can export a calendar from P6?

4 replies [Last post]
streetboy
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 22 Jun 2008
Posts: 3
Groups: None

Is it possible to export a calendar from primavera 6? if yes. how i can do it?

Replies

Tim Readman
User offline. Last seen 39 weeks 1 day ago. Offline
Joined: 23 May 2003
Posts: 51

You can export a calendar from P6 into a PDF form which will show the working days from the day one of the project to take into account all non working days. In p3 you could see this but not in P6 even up to version 8.2

 

try  this website

 

http://comviz.com.au/ 

 

Tim Readman
User offline. Last seen 39 weeks 1 day ago. Offline
Joined: 23 May 2003
Posts: 51

You can export a calendar from P6 into a PDF form which will show the working days from the day one of the project to take into account all non working days. In p3 you could see this but not in P6 even up to version 8.2

 

try  this website

 

http://comviz.com.au/ 

 

Raymund de Laza
User offline. Last seen 14 weeks 3 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Streetboy,

Here ist it.

1028
export.jpg