Whats Cost % Complete?

2 replies [Last post]
Jenny Ingco
User offline. Last seen 2 years 51 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear All Planners,

I just need to know what is the equation P6 use to calculate the Cost % Complete?

 

Thank you,

Replies

Jenny Ingco
User offline. Last seen 2 years 51 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Michael,

Thank you very much for your Help. Yes, I got it from the Hint Help.

God bless you,

Hanson,

Michael Lepage
User offline. Last seen 1 year 10 weeks ago. Offline
Joined: 11 Aug 2011
Posts: 37
Groups: None

Hi,

Taken right from "Hint Help": 

The percent complete of cost for all labor resources, nonlabor resources, material resources, and expenses for the activity. Computed as Actual Total Cost / At Completion Total Cost * 100.  Always in the range 0 to 100.

Try using Hint Help when choosing columns.  From the View menu, check Hint Help.  When you are choosing columns you'll get a yellow popup with a description of the highlighted column.

Hope that helps,

Michael

www.planacademy.com - Primavera P6 Tutorials from Beginner to Advanced