Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Relationship & Lags

3 replies [Last post]
Muhammad Asim
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 5 Oct 2011
Posts: 22
Groups: None

How can I get layput with Relationship Type and Lags?

 

Muhammad Asim

Replies

Anning Sofi
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

If your question was how to get a Activity Report Layout report (Predecessor and Successors) where there is a Layout format (Group by WBS, Activity Codes... etc), that is possible in P6.

An example is shown below (group by WBS)

906
report_page_1.jpg

kumar s
User offline. Last seen 9 years 2 days ago. Offline
Joined: 26 Jan 2010
Posts: 159

Dear,

Unfortunatlely you cannot get the relationship type and lag in any of the layouts.

you can only get it by exporting to spreadsheet format.

while exporting it to excel use the subject area as activity relationship instead of activity  in the modify template.

 

cheers

Daniel Limson
User offline. Last seen 5 years 22 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Muhammad,

Maybe you need to re-phrase your question, but anyway to give you an idea on relationships and lags

Types of relationship in a Precedence Method

Finish to Start Relationship  [[[[[[[1st[[[[[[[[[[F ---->S[[[[[[[[2nd[[[[[[[[[[  (2nd activity can only start when 1st activity is finished) now you can put a lag (+/-) and it would mean 2nd activity can only start (if you put 2 days lag) 2 days after 1st activity is finished

Start to Start Relationship   S[[[[[[[[1st[[[[[[[[[[    --->S[[[[[[[2nd[[[[[[[[[[ ( 2nd activity can start in parallel with 1st activity) if you put a lag of 6 days then 2nd activity can only start 6 days after the start of 1st activity

Finish to Finish Relationship  [[[[[[[1st[[[[[[[[[[[F ---->   [[[[[[[2nd[[[[[[[[[F (1st activity must finish before 2nd activity can finished. if you put a lag FF with 1 day lag, the 2nd activity will finished 1 day after 1st activity is finished.

Start to Finish Relationship  S[[[[[[1st[[[[[[[[[    [[[[[[[2nd[[[[[[[[[[F (1st activity must start before 2nd activity can finished)

 

Best regards,

Daniel

   

  •  
  •