Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Start and Early Start

7 replies [Last post]
moutaz aldeib
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Dear Planners,

What is the difference between Start and Early Start?

Regards,

Moutaz

Replies

omid khan
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 3 Jun 2013
Posts: 15
Groups: None

early start:

The earliest possible date the remaining work for the activity can begin.

This date is calculated based on network logic, schedule constraints, and resource availability. Early start dates can change as the project progresses and as changes are made to the project management plan.

  early finish:

The earliest possible date the activity can finish. Early finish dates can change as the project progresses and changes are made to the project management plan.

This date is calculated based on network logic, schedule constraints, and resource availability.

ef=es+duration

 

start(activities):

The current start date of the activity. For started activities, this is the actual start date. For not started activities, this is the planned start date until the project is scheduled. When scheduled, the start date field is set to the remaining early start date.

 

source:

p6 data dictionary 8.1

Raymund de Laza
User offline. Last seen 3 days 8 hours ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi,

If Data Date = Project Start Date then Early Start = Start

If Activity already Started then Start = Actual Start and Early Start is the start date of remaining duration.

If activity not yet started then Start = Early Start.

 

Regards,

Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Andrew,

Resource Leveling always puts its resultant dates into the Planned Dates columns.  It optionally also updates the CPM dates and the Start/Finish dates if you do not check the option, “Preserve scheduled early and late dates” in the Level Resources tab.  It takes a genius to keep all of these operations and options straight (especially because most of the operations are not even documented in the manual.)

Amit Parmar (PMP)
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Hi,

Consider the following scenarios and see how the Start Date changes

1) Activity is not started --------      Start=Early Start

                                                FInish = Early Finish

2)A ctivity has an actual start -----  Start=Actual Start  

                                                 Finish = Early Finish

3) Activity is Complete -              Start=Actual Start

                                               Finish = Actual Finish

 

Regards

Amit

Check out my blog on Primavera at http://www.primaverablog.in

 

 

 

 

Andrew Podolny
User offline. Last seen 1 year 20 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130

One addition, Ronald. Resources Leveling also affects start/finish dates.

Regards,

Andrew

moutaz aldeib
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Could you give me an example of that?

Regards,

Moutaz

Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Early Start dates are the result of the CPM calculation.  Start dates are a combination of Early Start and Actual Start dates.