Total Float - Is it possible to change the driver to within a WBS Code?

4 replies [Last post]
Chad Jones
User offline. Last seen 13 years 10 hours ago. Offline
Joined: 27 Jul 2011
Posts: 4
Groups: None
I have a schedule, with 1700 WBS Codes.
Within each WBS Code I have 5-20 activities.
I would like the total float to be driven from a certain activity within each WBS Code. So basically every WBS acts as it's own entity.
Right now, all Total Float is driven from the Latest Finish Date of the entire schedule.

Is this possible?
If yes, please give me a hint :)

Replies

Chad Jones
User offline. Last seen 13 years 10 hours ago. Offline
Joined: 27 Jul 2011
Posts: 4
Groups: None

Rock on Paul Harris!!!! Thank you very much!!

Paul Harris
User offline. Last seen 1 year 17 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

In the Tools, Schedule, Options, select "Make open ended activities critical" and all activities without successors will calculate their own critical path.

Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.eastwoodharris.com

www.primavera.com.au- a Primavera scheduling software resources site

Ram Kumar
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 26 Apr 2011
Posts: 4
Groups: None

Dear Jones,

 

I think that's the only way........................

Chad Jones
User offline. Last seen 13 years 10 hours ago. Offline
Joined: 27 Jul 2011
Posts: 4
Groups: None

Well, I've found out there is no way to globally change the driver for Total Float to per WBS.

 

What I need to do is set my last activity in each WBS to Mandatory Finish.