Updating P6 Weekly and Monthly Progress Backup

1 reply [Last post]
Henry Chiu
User offline. Last seen 11 years 8 weeks ago. Offline
Joined: 15 Jul 2011
Posts: 22
Groups: None

Hi Everyone,

 

I would like to solicit your input on how to save the P6 progress update. Normally in P3 you will save in a different file in order to recall the project history and be able to determine what particular period we need to analyse project performance.

Thanks

Replies

Justin James
User offline. Last seen 5 years 22 weeks ago. Offline
Joined: 19 Aug 2009
Posts: 32
Groups: GPC Qatar, TILOS

Hai Henry,

Go to TOOLS--- store period performance and save ur actuals , or else u can use the same P3 method here also by doing copy project option.

 

Regards

Justin