Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 - Timescale in PERT view?

3 replies [Last post]
Justine Butler
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 21 May 2009
Posts: 5

My first query on Planning Planet :-)

 

Is is possible to show a timescale in the PERT view in P6?

 

Thanks in advance for replies.

Replies

Justine Butler
User offline. Last seen 2 years 10 weeks ago. Offline
Joined: 21 May 2009
Posts: 5

Just what I thought, but wanted to check anyway.  Thanks for the replies.

 

Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Justine,

 

Time-scaled Logic Diagrams were a staple of the old P3.  Primavera has just announced that you can have then in the client/server version of P6 (to be called “P6 Professional”) in the Version 8 release due out around February 2011.  The web version of Release 8 (already out) does not have this.  In short, no you can’t currently put a timescale in the PERT view in P6.

waheed mirza
User offline. Last seen 12 years 31 weeks ago. Offline
Joined: 24 Nov 2010
Posts: 10

i don't know.let me check