P6 - Timescale in PERT view?

3 replies [Last post]
Justine Butler
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 21 May 2009
Posts: 5

My first query on Planning Planet :-)

 

Is is possible to show a timescale in the PERT view in P6?

 

Thanks in advance for replies.

Replies

Justine Butler
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 21 May 2009
Posts: 5

Just what I thought, but wanted to check anyway.  Thanks for the replies.

 

Ronald Winter
User offline. Last seen 3 years 18 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Justine,

 

Time-scaled Logic Diagrams were a staple of the old P3.  Primavera has just announced that you can have then in the client/server version of P6 (to be called “P6 Professional”) in the Version 8 release due out around February 2011.  The web version of Release 8 (already out) does not have this.  In short, no you can’t currently put a timescale in the PERT view in P6.

waheed mirza
User offline. Last seen 12 years 12 weeks ago. Offline
Joined: 24 Nov 2010
Posts: 10

i don't know.let me check