Joined: 19 Apr 2008
Posts: 3

I have a baseline added in the current schedule. Could anybody tell me how to show the baseline late bar?

Replies

Paul Harris
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

This is one of the many issues I have with this software.

The olny way I have found to display the Baseline Late dates is to create a copy of the schedule and set all tasks to ALAP and then set this schedule as a Baseline.

Regards

Paul E Harris

Directo r

Eastwood Harris Pty Ltd http://eh.com.au