Dear Friends,
I have prepared a cost loaded P-6 Program. In the program I loaded the cost of each activity from the BOQ price. I put the cost of each activity in the budgeted cost (in expenses, in the activity detail tab).
My Manager wants that, for certain activities the cost loading should be linear or some polynomial and not uniform over the activity (actually the accrual type in budgeted cost are only- uniform over activity, End of activity, start of activity).
The idea of my Manager is to have a comparison curve (S-curve) between the actual amounts of work done at site (from the price of the activity in the BOQ. This amount is to be invoiced) and the Planned amount of work (this is also based on only the BOQ price).
So please help me in
(1) How I can get linear cost loading against the activities instead of uniform over the activity?
(2) Am I putting at the right places the cost of activities (i.e. in the budgeted cost) or i need to put the BOQ prices of the activities at some other place?
(3) Is there any better way to achieve the objective of preparing the comparison curve?
I am new to primavera software.
Thanks and Regards
Faisal Hashmi
I am very new to primavera software.