Restoring an Updated Schedule to Original Schedule

1 reply [Last post]
Ariel Malibiran
User offline. Last seen 5 years 52 weeks ago. Offline
Joined: 6 Mar 2009
Posts: 54
Guys’ I’m just thinking if for instance, I have updated and rescheduled an schedule for the first time without saving a copy of the schedule or maintaining and assigning a baseline to that schedule...is it possible to restore it to the original/unupdated one? if so, how? i know i won’t happen in actual, i’m just currios ...

thanks!

Replies

Rodel Marasigan
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Ariel,
It’s easy. Just copy the updated schedule and remove the actual using global change then use that as a baseline.