Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Showing Two Critical Paths in P6

7 replies [Last post]
Ijaz Ahmad
User offline. Last seen 8 years 14 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Hello Guys,
I am having problem to show two different critical paths in the same schedule at the same time. One path has Total Float = 0 and the other path has Total Float = 112. The problem is when I set the option "Total Float less than or equal to" to 112, those activities that fall in the range 0 to 112 also show up as critical. Is there a way that my one path shows only those activities which have zero total float and the other path that has total folat 112 only.
Any help will be highly appreciated.
Thanks
Ijaz

Replies

Shazia khan
User offline. Last seen 13 years 11 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139
Hi,

Please check your setting.

Hit -f9 -option-Define crictical activities. Tick total float less then or equal to 0h,
also check " Compute total float as "finished float=late finish-Early finish"

Calender for Schedulling relationship lag.

"Predecessor Activity Cal,

Check the above setting,

if setting is correct and problem stil exist then change the duration , and relationship,and lags

HTH
niles luo
User offline. Last seen 13 years 50 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None
hi,
I think you can create two filters, one is total float =1 and the other is total float is 112. Then you can display one CPM when select one of above filters and filter ’critical’ .
Best Regards.
Rola Sabbah
User offline. Last seen 11 years 26 weeks ago. Offline
Joined: 5 Dec 2009
Posts: 61
HI
why would we need to show 2 paths? is it best practice to have more than one?
how can we make it in p6?
Shareef Abdul Azeez
User offline. Last seen 3 years 44 weeks ago. Offline
Joined: 19 Sep 2005
Posts: 183
looks likee some of us still have to start up from the basics...

Shazia was right on one thing "if the problem still exists change the duration, links..."

there can be two or more critical paths for a programme which has two or more areas or sectors running parallel and each of which finally merge to drive the project finish date.
But the scene here is totally different. The path has a total flot of 112 days.....

Looks like you want to create your own critical path.

If you still are sure the path should be critical,then change the links and reduce its float..

Best Regards
Shareef A Azeez
Ijaz Ahmad
User offline. Last seen 8 years 14 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None
Hi Azeez,
Thanks for your comments. As you already know a program can have more than one areas running parallel and it is also true that these two areas merge to drive the project finish date. The same is the case with my project. My second area has a chain of activities which all are showing a float of 112 hrs. I want to indicate this chain of activities as a second critical path. And here I come to my original problem that how can I show this second path while still showing a critical path of zero float in my first area.
Thanks
Ijaz
Shareef Abdul Azeez
User offline. Last seen 3 years 44 weeks ago. Offline
Joined: 19 Sep 2005
Posts: 183
Hi Ijas

I would like to know why you want to make a path with 122 TF critical....

* Is this because your Project manager or construction team have recommended from their experience ?

* Or u want it to be critical for claims ?


The only way is to bring down the TF on the second path to zero ( or less than the figure you want to show critical say TF less than 5).



Rodel Marasigan
User offline. Last seen 15 weeks 2 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Ijaz,
Critical path means longest path or zero float or as defined float. Total float is the amount of time that activity can be delay but not delaying project completion date. If you have 112 float then it’s far from being critical.
If the cause of 112 float is because of an open logic then P6 has an option to select to make open ends as critical when running schedule (F9).