P6v7 Tracking - EV curve

1 reply [Last post]
Deepak Jain
User offline. Last seen 10 years 29 weeks ago. Offline
Joined: 14 Jan 2006
Posts: 31
Hello all,

Under the tracking project , for project profile , PV and EAC curves are plotted but not the EV though it shows the EV values in spreadsheet but not in profile , could someone please explain why ?

Thanks in Advance.
Deepak

Replies

Rodel Marasigan
User offline. Last seen 17 weeks 18 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Deepak,

Select View-> Layout-> New-> Project Gantt/Profile and name your layout so you can use it again. Once display right click on profile and tick Earned Value, Forecast etc.. to show in the profile.