3 replies [Last post]
tasnim yusoff
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 1 Jul 2010
Posts: 13
Groups: None
Hi,

I have problem regarding duration with my primavera v6.7.
I export files from Primavera v6.2.1 to Primavera v6.7 but the original duration incresed but the start and finish date is still da same date. I checked the calendar and admin preference, it the same setting as my P6.2.1 setting. The original duration for all of da files that i export to P6.7 changed.

Can someone help me regarding this issue?

Replies

tasnim yusoff
User offline. Last seen 9 years 28 weeks ago. Offline
Joined: 1 Jul 2010
Posts: 13
Groups: None
Hi,

Thank you. It solved now :)
Rodel Marasigan
User offline. Last seen 6 weeks 2 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Tasnim,
Duration is calculated based on activity caledar assigned as limitation of working period for date and Hours per time period for time unit set (i.e. 8h/d, 40h/w, 173.3h/m etc...)
check if Hour per Time Period is the same as calendar total working period per day and the same setting on P6.2.1
Andrew Dick
User offline. Last seen 9 years 5 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 295
Tasnim,
Check each calendar you have assigned to the activities in the schedule. The units/time are now set at the calendar level. If this is out of sync with what you had used originally then you may have an issue.

Also I’m not sure how the WBS durations are calculated if you have different calendars assigned under the same WBS, possibly defaults back to the admin preference for that calculation???

Andy