Store period performence

3 replies [Last post]
shaik Barkatulla
User offline. Last seen 8 years 18 weeks ago. Offline
Joined: 13 May 2010
Posts: 13
Dear All,

If i click for store period performence what should be the financial period date? (should be equal to data date???), please clarify.

Regards

Replies

Rodel Marasigan
User offline. Last seen 15 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Shaik,
If your cut-off weekly is Saturday then create financial period date every Saturday.
shaik Barkatulla
User offline. Last seen 8 years 18 weeks ago. Offline
Joined: 13 May 2010
Posts: 13
Dear Rodel,

Thank you very much,

If i am updating for this week the data date is coming by default as 29-May-10, then financial period value also to be set as 29-may-01.
Rodel Marasigan
User offline. Last seen 15 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Shaik,
Using period performance you need to define financial period date first. Your financial period will depend on your progress cut-off. It can be weekly, monthly which can be set by batch. If you are tracking your project weekly and producing s-curve, EV, Activity spread value, resource spread value every month only then financial period should be define as monthly. If producing this type of report weekly then your financial period should be weekly.