Actual Labor Units in between Total,Spent & remaining..

1 reply [Last post]
Izam Zakaria
User offline. Last seen 7 years 32 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Guys,

As reference made above, I’ve 20k Budgeted Labor Units which have been spent about 9k. But the remaining labor units present 10K. So where is another 1K gone?

This should be computed automatically right?

Replies

Rodel Marasigan
User offline. Last seen 6 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
izam,
It depends on your settings and how you update your progress. (i.e. Duration type, % complete type, Project Resource assignment calculation, resource settings) All those settings are controling how Primavera response on updating progress.