OD & RD Equal Zero When Converting from P6 to P3 (????)

2 replies [Last post]
Benjamin Mora
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
My issue is that when I am using P6 and converting to P3 the OD & RD become zero in the P3 version of the schedule.

Here are my settings:
-All tasks = physical % Complete
-Drive Activities Dates by Default = unchecked
-Duration Type = Fixed Duration & Units\Time
-All units are zeroed out
-Recalculate Actual Units & Cost when Duration % complete changes = unchecked
-Link Budget & At Completion for not Started Activities = Checked
-Reset Remaining Duration & Units to Original = Checked.
-All activities = Task Dependent.

By the way, this schedule was originally a conversion from P3 that went to P6 and is now going back to P3.

Any clues?

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Ben you are not an idiot you caught the problem and solved it. I believe that during the conversion dirve activity dates by default was checked in p6 and this make the resource in p3 a driving resource.

Benjamin Mora
User offline. Last seen 11 years 18 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
Disregard because I am an idiot. In the Assignments window, each assignment needed to have the Resource Driving box unchecked. Problem solved.