Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6-Summery of percent complet

1 reply [Last post]
Mohammed Abo El Magd
User offline. Last seen 15 years 5 weeks ago. Offline
Joined: 29 Nov 2004
Posts: 46
Groups: None
Dears,
Does anybody know how P6 calculate the percent complete on the WBS summery level? As example,

Finishing works PC% =?
Internal finishing PC% = 50%
External finishing PC% = 40%

How P6 calculate the PC% of Finishing works level?
Regards

Replies

Dieter Wambach
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Mohammed

you can find those formulas in the Help function, e.g.:

"Schedule % Complete: specifies how much of the wbs’s baseline duration has been completed so far. Computed based on where the current data date falls between the activity’s baseline start and finish dates. If the data date is earlier than the baseline Start, the Schedule % Complete is 0. If the data date is later than the BL Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the wbs duration should be currently completed, relative to the selected baseline." (end of quotation)

There are more %-complete types in P6.

Regards
Dieter