The equivalent of the fragnet in P5

2 replies [Last post]
M. Kamel Bessekri
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 2 Jul 2009
Posts: 27
Groups: None
Hi There
could some one indicate me what is the equivalent of the fragnet (p3) in the p5

thanks

Kamel

Replies

Joao Ribeiro
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64
The equivalent should be Methodology Manager.

HTH
Dieter Wambach
User offline. Last seen 7 years 23 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Kamel

P5 has all projects in one database. It is very easy to copy parts from one project to another.

We created small projects with those typical sequences, which are just copied into a new project.

Use the view: WBS for such actions.

Regards

Dieter