Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

p6 updating, actual vs baseline, physical %vs schedule%

No replies
Num Lock
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 15 Oct 2006
Posts: 27
What is the use of UPDATE PROGRESS in tools menu?

How about the UPDATE option (including the choices when you click here) in Maintain Baseline dialog box in project menu?

How can I use them when I’m doing the first update for actual accomplishment and the succeeding updates.

Kindly elaborate in details what are the steps in updating, for example i’m using physical % complete (actual) vs. schedule % complete (baseline).

Where can I see the TOTAL physical % complete vs. schedule % complete.

Thank you.