Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Update a Baseline with Current Actuals/Progress

4 replies [Last post]
Edniel Recamadas
User offline. Last seen 14 years 3 days ago. Offline
Joined: 30 Apr 2009
Posts: 40
Groups: None

Dear PP'ers,

I've been involved recently at ongoing buildings project (now in 7th month of a 1.5 year contract) and when I compare the update using the Claim Digger in P6 there have been a lot of changes done by the previous planner on the updated schedule.

What's the best way (most reliable) to update the baseline using the current actuals/progress.

Thanks for the assistance,

Edniel

Replies

Rockzy Sales
User offline. Last seen 13 years 43 weeks ago. Offline
Joined: 19 Dec 2010
Posts: 19
Groups: None

I think what he wanted is to Revise the Baseline reflecting the actuals and logic changes

 

Will making your updated schedule as your new baseline be different from what you wanted? A little work around to make your planned dates = current dates and make it your new baseline or revised baseline?

 

Regards,

the Rock

Raymund de Laza
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi Edniel,

Attach the Baseline Schedule to the Updated Schedule. On the Manage baseline window click on Update then work out on the data you wish to update into the baseline from Updated.

 

Hope this will help you.

 

Regards,

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Edniel

In Asta Power Project it is possible to set all progress data to zero and get back to the original programme - then start again.

Is this not possible in P6?

Best regards

Mike Testro

Damian Smith
User offline. Last seen 4 years 12 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 12

The baseline is the baseline and needs to stay as the baseline. What you need to do is update a copy of the baseline and call it a progressed programme.

If you have got the actual start and finish dates, then update the progressed programme with this information and compare it to the baseline.

If there has been numerous changes and the plan does not reflect what is actually going to happen from this point onward (ie wildy out of control), then perhaps ask the client or PM and tell them that you want to submit a new updated baseline. This new baseline will still have progressed information on it, ie what has happened, but maybe you can re sequence the job and or add new information and start from fresh. (this is last resort though)

Otherwise, you could just change / update the progressed progrmame to reflect what is happening in the real world.