Cumulative Early and Late Curves

R
Rama Krishnan 👤 Member for 19 years 7 months

If you have copied activities from another project , constraints of previous project are also copied such as project finish by date or activity’s must complete by.

These could introduce unwanted negative float



Rama

I
Ian Adan 👤 Member for 21 years 7 months

I guess you have negative float on some of your activities.