P3e version 5- Baseline problems

4 replies [Last post]
Norul Faezah Nohi
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 17 Jul 2008
Posts: 8
Hi all,

I have problems with P3e baselines.Whenever I tried to copy a file which was baselined to a new one, the old previous baseline didnt copy as I thought it should be.Instead, the baseline bar in the new file shifted follows the progress bar even though I have not re-schedule it yet i.e. both the data dates are still the same.What I did just copy the first file to a new file. Looking for any P3e experts to help me or provide /share problems/answers why this happens.
.thanks.
Norul











Replies

Norul Faezah Nohi
User offline. Last seen 15 years 17 weeks ago. Offline
Joined: 17 Jul 2008
Posts: 8
Dieter Wambach,

Thanks for the reply :). I will try to propose this to my company to use P6 if possible. At the moment , I always encountered this baseline problems/inconsistencies everytime!

**Norul**
Dieter Wambach
User offline. Last seen 7 years 32 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Prem
This item is solved in P6, so you can copy BLs together with the project. During the call for copy there is a screen where you can select those BL to copy and those for not.
Dieter
prem kumar,
User offline. Last seen 13 years 19 weeks ago. Offline
Joined: 9 Mar 2005
Posts: 14
Groups: GPC Qatar
but why exporting baseline is not copied along with the project even in P6
Dieter Wambach
User offline. Last seen 7 years 32 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Norul
This is solved in P6. In P5, baselines were not copied together with a project.
You have to ways: Upgrade to P6 or unlink ("Restore") the BL --> Copy project + BL --> create BL again out of this BL-project.
Regards
Dieter