Ah,, think I may have just sussed it,, I can take a straight copy and paste from the Resources Assignments view having amended the Spreadsheet View Fields to display Actual-Budget-Remaining,,



happy days



cheers

Jon

J
Jonathan Ward 👤 Member for 19 years 5 months

Actually a work around for this would be a separate report that gives me Actual Hours against Resources,, anyone know if this can be done?