What is the difference between P3 and P6?
Forum Sponsor
Top Posters
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
Can we create a graph, with duration on x-axis and % progress in project on y-axis in Primavera?
i believe yes, you can even define it manually (physical progress)
OK, that’s the Primavera blurb. Now what are the real differences in functionality?
I hear that with P6, you can’t record a different Earned Value against different Resources against a single activity. e.g. if the Activity is "Construct Concrete Wall" and it has Resources like "Formwork Material, Formwork Labour, Rebar Material, Rebar Labour, Concrete Material, Concrete Labour". Is it possible to report say 100% progress against Formwork Material and Labour but 0% against the other Resources, thus Earning the Budget Cost of Formwork only... like we can with P3?
Thanks