Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

any thumb rule to check schedule

2 replies [Last post]
Mallesha Chandra ...
User offline. Last seen 13 years 20 weeks ago. Offline
Joined: 3 Apr 2008
Posts: 21
Does any body have some thumb rules to check ,whether schedule & logic is ok.Whether total float is the deciding factor of good schedule. If so What is the maximum total float value we can allow in a schedule

Replies

Abhijit Kale
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 126
Groups: None
Hi Ronald,

good one.
Regards,
Abhi
Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
I presented a paper at the 2002 Primavera User’s Conference titled, "Baseline Schedule Analysis" that might fit the bill. You can find this and other papers at http://ronwinterconsulting.com/published.htm. Good luck.